Change orders for remodeling contractors: get paid for "while you're here"
💬 CommentsHalfway through a bathroom the customer says: "While you're here, can you also move that outlet and tile the niche?" You say sure. Three weeks later the last invoice is higher than the estimate they signed, nobody remembers what was agreed, and you are arguing about money on the final day of a job that went well. The work was fine. The paper was missing.
When you need one
- The customer adds work: one more outlet, a second coat, a bigger vanity.
- The customer removes work: they decide to keep the old floor after all.
- You open a wall and find something nobody priced: rot, old wiring, a pipe where the niche was going.
- A material changes and the price moves with it.
- Anything that moves the finish date.
What goes in it
- The change in plain words: what is added, removed or swapped, and where.
- The price of the change, line by line, with tax.
- The new contract total, so nobody has to add it up.
- What it does to the schedule: how many days, and the new finish date.
- When the extra is paid.
- A signature and a date.
The one rule: no signature, no work
Most lost money on extras is not from customers who refuse to pay. It is from work done on a nod, by a crew that wanted to be helpful, and never written down. Make it a rule for yourself and for everyone on site: when the customer asks for something outside the signed scope, the answer is "yes, I will send you the change today", and the work starts after it is signed.
It takes ten minutes. A message like this is enough to go with it:
Hi [name], you asked us to add [what]. I have sent you a change order: it adds [amount] to the contract and [N] days to the schedule. Please look it over and sign, and we will start on it as soon as it is signed.
When work comes off the job
Do not simply bill less. The signed contract still shows the old number, your own books show a profit you never made, and sales tax gets figured on work that was never done. Write the removal down the same way as an addition: a change order with a minus, signed by the customer. The trade calls it a deductive change order.
How it works in WorkTime CRM
Once the customer signs an estimate, its scope is locked: nobody edits a signed document by accident. To change the job you press "Create Change Order" on the estimate, or "+ Change Order" in the project under Money → Estimates. You add the lines, send it, and the customer signs it.
The project contract is always the sum of the signed estimate and every signed change order, so the Contract, Spent and Profit numbers on the Money tab are right without anyone retyping them. A change order takes the same tax rate as the job, and the sales tax on the project corrects itself when it is signed.
For work taken off, type the price with a minus. When the customer signs, the contract and the tax go down, and the credit shows under the project invoices with an "Apply" button that lowers an unpaid invoice by exactly that amount.
Questions
Do I need a change order for a small extra?+
Yes, if it changes the price or the finish date. Small extras are the ones that pile up unbilled. If you decide to do something for free, write it down anyway with a zero: the customer sees what you gave them. Some states have their own rules on written changes to home-improvement contracts; check yours.
The customer cancelled part of the job. Can I just lower the last invoice?+
Write a change order with a minus and have it signed first. In WorkTime CRM the signed credit then appears under the project invoices, and one press lowers the unpaid invoice by that amount. An invoice that is already paid is not edited: that is a refund.
Does it cost extra?+
No. Change orders are part of the WorkTime CRM plan: 7 days free, no card needed, then $99 a month per company.
💬 Discuss this article
Comments, likes and Ivan's answers live on the original page.
Open the comments →Work Time CRM